The procedures of the water and sewerage connection to the object Print
Friday, 09 December 2011 10:10

1. A person wishing water and sewerage connection to the unit must take an appropriate technical term. To obtain the technical condition, the consumer have to apply to the company Ltd ”Batumi Water”, for which he must present a site plan, as well as the information about the water used by the facility. To accept the technical rules it is mandatory to pay an appropriate fee set by Ltd ”Batumi Water”.

2. After accepting the agreement, it is needful to submit a request to Batumi Hall to be permitted to dig the streets or the other running areas and pull water or sewage pipes in it.

3. The city hall will give the person tour paper, after which it is obligatory to be signed the agreement by the mentioned organizations in the sheet and also the organizations must be warned before beginning the installation works.

4. After accomplishment of the third point (abovementioned 3rd section) the person himself can or through the appropriate organization carry out the installation of the water and sewage pipes.

5. The person must inform Ltd “Batumi Water” about fulfilling of the installation, after which the company itself carries out the connection works.