The procedures of Electric Power network connection Print
Friday, 09 December 2011 10:13

1. At first the consumer to adopt the technical condition must make a request to Ltd “Energo Pro Georgia” in written form, in the statement the user must indicate the capacity and the output of the equipment of the facility, also the total output of the Electric Power.

2. After gaining the technical requirement, the person have to apply to the design firm, to make project the design agreement must be carried out by the company ”Energo Pro Georgia”.

3. After the project agreement, the consumer will be able to start the works of electric power installation.

4. When the installation is over, the user files the request in written form to the company” Energo Pro Georgia” and the person demands to be inspected the performed work. (According to the project agreement)

5. When the works complete, the consumer requires to be chased the subscriber.

6. Ltd”Energo Pro Georgia” determines the expenditure of the technical terms made by ltd “Energo Pro Georgia”.